top of page
STATUS:
APPROVED
299A1 - Lawton Chiles ES
General Information
Subcontractor:
Atlas Apex Roofing, LLC
Subcontractor Project Manager:
TERRY CHEUNG
Phone #:
9545651567
Email:
SECTION #1: Job-Site Specific Accident Prevention Plan
Please download the documents you wish to review.
Key personnel
Emergency List
OSHA 300
Appointment Letter
Basic Safety AHA:
7.-
Do you plan to perform work at heights greater than 6 feet at any time using ladders, scaffolds, or any aerial work platform (AWP)?
YES
8.-
Do you plan to perform any excavation work at any point during your project?
NO
9.-
10.-
Do you anticipate performing any electrical or demolition work at any stage of your project?
NO
Attach a copy of your Certificate of Insurance (COI):?
SECTION #3: Equipment Certification (If Applicable)
Do you plan to use any of the following equipment during your activities on the project?
Scissor Lift Use? | Boomlift? | Forklift? | Welder? | Heavy Equipment? |
|---|---|---|---|---|
NO | NO | YES | NO | NO |
If you answered “Yes” to any of the previous questions, please attach the certificate(s) of the operator(s) below.
Person Responsible for Submitting the Information:
Name:
Nick Soranno
Position:
ASSISTANT PROJECT MANAGER
Email:
Signature:
⚠️ For LEGO CO Safety Department Use ONLY
Observations:
1.- Please use the Basic Safety AHA.
09/17/2025 1:25 PM
Observations:
1.-CORRECTED
09/19/2025 9:44 AM