294B1 - Lakeview ES- Reroofing
Please address the following observations ONLY, and change the status to "READY TO REVIEW".
If you have any questions, please contact me by email at rq@legocc.com.
Thank you.
Observations:
1. - As discussed during our phone conversation today, I kindly request that you submit the documents in the proper manner. Thank you for your attention.
09/08/2025 12:51 PM
NEW NOTES/////
- Please submit the correct OSHA 300A. You attached the Safety Plan instead of the OSHA 300A.
- Please submit the Basic Safety AHA. Any other AHA will be rejected.
- Attach the OSHA 10 certificates of your workers.
09/09/2025 9:19 AM
NEW NOTES/////
- CORRECTED
- CORRECTED
- CORRECTED
09/09/2025 2:38 PM
MOBILizATION APPROVED
General Information
Subcontractor:
Apex Roofing USA LLC
Subcontractor Project Manager:
Apex Roofing USA LLC
Phone #:
5615654537
CODE:
3456989640
SECTION #1: Job-Site Specific Accident Prevention Plan
Please download the documents you wish to review.
Accident Prevention Plan
Key personnel
Emergency List
OSHA 300
Appointment Letter
Basic Safety AHA:
7.-
Do you plan to perform work at heights greater than 6 feet at any time using ladders, scaffolds, or any aerial work platform (AWP)?
8.-
Do you plan to perform any excavation work at any point during your project?
9.-
10.-
Do you anticipate performing any electrical or demolition work at any stage of your project?
Attach a copy of your Certificate of Insurance (COI):?
11.-
SDS
SECTION #2: Required Training
OSHA 30
OSHA 10
First Aid CPR
Fall Protection
SECTION #3: Equipment Certification (If Applicable)
Do you plan to use any of the following equipment during your activities on the project?
If you answered “Yes” to any of the previous questions, please attach the certificate(s) of the operator(s) below.